We replaced a roof that collapsed over the production area. This required shoring the utility lines, removing the existing roof, and replacing it with new structural steel and deck.
We installed new precision sand equipment including core machine, generator, mixer, scrubber, cyclone, and robots.
For a plant modification project, we erected new interior mezzanine, process ceiling support steel, and process area framing.
We shored a platform and the conveyor between two buildings. At a later date, we supplied and installed new support steel onto a new foundation.
We disassembled a cell of Lambda equipment, then crated, boxed, and skidded, as required, and then loaded out equipment for shipment.